Project Timeline: September 2022 – March 2025
Concrete Cast: 1,300 m³
Rebar: 41 tonnes
Formwork: 1,100 m²
Structural Steel: 81 tonnes
G4 Mining and Civils (Pty) Ltd was entrusted with the construction of two pre-cooling towers and one three-cell condenser cooling tower at Northam Platinum’s Zondereinde Mine. This project involves the placement of a substantial volume of concrete, alongside the use of innovative formwork techniques, working at height, and the integration of complex structural elements.
The scope and scale of the project presented an opportunity for our team to demonstrate our expertise in delivering large-scale infrastructure projects safely and efficiently, even in challenging environments.
This project highlights G4 Mining and Civils’ ability to manage and execute large-scale, technically complex projects, demonstrating our commitment to quality, safety, and innovation in every aspect of our work.