Steelpoort

Richmond Steel Bridge Construction

Location: Steelpoort
Project Duration: July 2025 – February 2026
Service Areas: Bulk Earthworks | Reinforced Concrete
Project Team:

  • Site Agent: Johan Els

  • Contracts Manager: Stephen Howard

A vital bridge over the Dwarsrivier was washed away, requiring urgent replacement. The G4 Mining & Civils team was appointed to coordinate the geotechnical investigations, contribute to the bridge design, and manage the construction of the new structure.

https://g4miningandcivils.co.za/wp-content/uploads/2026/03/Richmond-LI.webp

Scope of Work

The following key elements formed part of the project scope:

  • Construction of a 25 m clear-span steel bridge with sufficient freeboard above the 1:50-year flood level.

  • Reinforced concrete abutments designed to TMH 7 Part 1 & 2 specifications.

  • Adjustment of the vertical alignment of the existing district road to suit the new bridge level.

  • Embankment works and erosion protection measures.

  • Demolition and removal of the existing damaged bridge structure.

Geotechnical Investigation

Western side of the river:
Competent rock horizon was encountered at approximately 3 m below natural ground level (NGL). Test pits revealed very soft rock anorthosite with an in-situ bearing pressure of 300 kPa.

Eastern side of the river:
An alluvial layer consisting of cobbles, boulders, and silty coarse sand was identified. The saturated horizon caused significant washout and sidewall collapse during excavation, with an in-situ bearing pressure of 150 kPa. Very soft rock anorthosite was encountered only between 5 m and 8 m below NGL.

Foundation Design

Based on the geotechnical findings, piled foundations were recommended for both abutments. This solution ensures stability and provides a reliable founding for the steel bridge structure.

Project Timeline

The project is scheduled for completion within 7 months, from July 2025 to February 2026.

Project Workforce

A total of 25 personnel were involved in the project, including permanent staff and contractors.

Materials & Quantities

  • Concrete Poured:  790m3
  • Structural Steel: 46 tons
  • Hours worked: 26918 and all LTI Free
  • Reinforcing: 41 tons